The First Phase of Paderborn's Recycling Center Modernization: A Covered Drop-Off Elevated Platform by Modulo Wertstoffhöfe GmbH
Thanks to the elevated drop-off platform, this facility remained operational throughout the construction work and the remaining construction phases in the rear section of the site could proceed without major disruptions.
Modulo Wertstoffhöfe GmbH

The recycling center at An der Talle in Paderborn, operated
by the Waste Management and Municipal Cleaning Department of Paderborn (ASP (Abfallentsorgungs- und Stadtreinigungsbetrieb Paderborn)),
was originally constructed in 2008. The facility featured a simple layout
consisting of a ground-level paved area of approximately 3,700 m², where
containers could be accessed either from the front or from above via stairways.
Within a few years, steadily increasing visitor numbers demonstrated that the facility
would soon require expansion. Annual usage grew from 217,000 visitors in 2009
to more than 268,000 by 2018 and later exceeded 300,000 vehicle entries per
year. According to user surveys, the recycling center's popularity was primarily
due to its fast service with minimal waiting times, the largely free disposal
of recyclable materials, and its generous opening hours. However, the growing
visitor numbers also created significant operational challenges, particularly
during peak periods on Saturdays when more than 200 deliveries per hour could
occur.
Another major drawback of the original design was the requirement for customers
to carry heavy materials, particularly green waste and wood, up stairways to
reach the containers. This proved especially difficult for elderly users and
reduced overall customer convenience. Consequently, ASP decided not only to
enlarge the facility but also to fundamentally improve its accessibility and
operational efficiency.
ASP secured a long-term lease on an adjacent plot of land of similar size and acquired additional neighboring property. This made it possible to expand the existing facility at the same location rather than relocating to a new site. The recycling center ultimately increased in size to approximately 9,500 m² and was redeveloped in three construction phases.
Modulo Wertstoffhöfe GmbH (Modulo Recycling Centers) was responsible for the design, planning, and construction of the first phase. The ModuloSystem was selected as it would provide the greatest benefits: a modular precast concrete solution of a ramp system and an elevated and covered drop-off platform with additional storage space. The modular and reusable elements in the design offers long-term flexibility, allowing the facility to be expanded further or even relocated in the future if necessary, while fully supporting sustainability and circularity objectives.This solution allowed the facility to remain fully operational during construction, which was essential due to the high number of annual visitors. By completing the first phase, the construction on the remaining sections of the site could continue with minimal disruption to daily operations.

The new elevated drop-off platform enables customers to drive directly onto the structure via an entrance ramp, unload their waste into containers positioned below, and exit the site using a second ramp. This eliminated the need to climb stairs and makes the disposal of bulky waste, green waste, wood, scrap metal, tires, rigid plastics, and other materials significantly more convenient. The ramps are equipped with underfloor heating, allowing safe operation during winter while reducing the maintenance required to manage snow and ice.

The facility contains ten container bays, four of which are equipped with
specially designed chutes that make the disposal of green waste particularly
easy. Other waste streams—including residual waste, paper, and recyclable
materials—continue to be collected either in compactor containers or in
front-loaded ground-level containers located within the original section of the
recycling center.
A key feature of the new design is the complete separation of customer traffic
from operational vehicle traffic, with only a few controlled crossing points.
Multiple traffic routes were incorporated to accommodate increasing visitor
numbers while minimizing waiting times and improving overall site safety for
both customers and staff.
The redesigned facility can accommodate approximately 13
vehicles at the same time, and with an average unloading time of five minutes,
the platform is capable of serving around 150 vehicles per hour.
The elevated platform makes more efficient use of the available land by
creating extensive covered storage space beneath the structure. This area is
used for storing recyclable materials and equipment and for receiving reusable
goods that are later sold through a second-hand store operated by the Red
Cross.
In addition, to improve environmental performance, the roof of the elevated platform was equipped with a photovoltaic system combined with battery storage. The installation was designed to generate electricity for the operation of compactors, roll packers, lighting, electric forklifts, and other electrically powered vehicles and equipment while providing on-site energy storage to support the facility's own power supply. The covered drop-off area also encourages a more even distribution of visitor numbers throughout the year, as customers no longer need to avoid the facility during periods of rain.

Modulo Recycling Centers supported the project from the earliest planning
stages through construction. According to Technical Director Mr. van Niekerk,
the consultation and planning process was completed in approximately three
months, considerably faster than typical projects, and the elevated platform
itself was constructed in just six weeks. The use of modular precast concrete
elements allowed the main structure to be assembled within one week, after
which subcontractors completed the remaining work. Close collaboration between
Modulo, ASP, and the project architect, supported by rapid concept development
using sketches and preliminary designs, contributed to the project's
accelerated schedule.
Despite the challenges of carrying out construction while the facility remained
in operation, user feedback following completion were overwhelmingly positive,
reflecting significant improvements in accessibility, traffic management,
safety, sustainability, and overall customer experience.
Regener, D. (2019). Erweiterung Recyclinghof Paderborn [Article in VKS News, PDF]. VKS News. https://www.modulocare4circulair.nl/wp-content/uploads/2019/10/VKU-news-Erweiterung-Recyclinghof_VKS-News09-2019_Auszug-1.pdf
EschstraĂźe 111
D - 48703 Stadtlohn
phone:+49 2102 420 840
Energy from Waste: Istanbul’s Contribution to Reducing Global CO₂ Emissions
Cost-intensive aftercare of the Gallenbach household waste landfill, Germany
PV installations of ZMS/OVEG Schwandorf - Sustainable Regional Value Creation and Decarbonization in the Oberpfalz Region
RFD from Industrial- and Household Waste in Allgaeu, Germany
Additional Floor Space and Flexibility at the Recycling Center in Teltow, Germany
Reutlingen Makes “Plastic-Free Organic Waste” a Reality!
E[co]work Enabling Safe, Inclusive and Circular Solutions for E-Waste Management in India
Through the BEEAH Recycling vertical, the BEEAH Group has made great headway towards a zero-waste solution, in Sharjah currently achieving a diversion rate of more than 76%
Lean Gas Instead of High-Temperature Flare at the Blomenhof Landfill, Neumarkt i.d.OPf. - Climate Protection Through Landfill Remediation